In connection with numerous complaints and signals received from citizens regarding the implementation of the project: “Reconstruction of “Opalchenska“ street from “Alexander Stamboliyski“ blvd. to “Slivnitsa“ street - II STAGE “Reconstruction of “Opalchenska“ street from “Todor Aleksandrov“ blvd. to “Slivnitsa“ blvd., including an outflow channel along “Slivnitsa“ blvd. to its discharge into the Vladayska River and accompanying infrastructure“, located in the “Vazrazhdane“ area - Sofia Municipality, financed under the Investment Program for Municipal Projects 2024-2026, the Ministry of Regional Development and Public Works, together with the Directorate for National Construction Control, carried out several inspections of the above-mentioned construction - on site and according to documents.
The inspections established the following:
The results of laboratory tests show that during the construction, additional materials were used that did not meet the requirements of the project; the Bulgarian Civil Code; the technical rules and norms and the requirements specified in Art. 169a, para. 1 of the ZUT. Ineffective control over the construction was exercised by the construction consultant and by the Sofia Municipality as the contracting authority.
In view of the above, the DNSK will issue an order pursuant to Art. 224, para. 1, item 3 of the ZUT to suspend the implementation of the construction on ul. “Opalchenska“ until the violations are eliminated.