The Municipality of Plovdiv will give a total of 7 properties with a total area of over 69,000 sq m, needed for the new section of the city's Ring Road. The commission responsible for the property policy of the city authorities has given its consent in principle to the donation of the plots, which are municipal private property. The Municipal Council will have the final say under the hills.
They are in connection with the developed Plot Plan of the connection between Skobeleva Maika and Asenovgradsko Shosse, Trafficnews specifies. In addition to these properties, the RIA must also acquire properties of the “Rhodopi“ municipality, as well as alienate private ones.
We recall that the project for the Southeast Bypass is being revised again, and the Plovdiv Municipality gave 69,000 leva to the company “Patproekt“ 2000, which is the copyright holder.
The announcement makes it clear that an update of the project is necessary, due to partial changes and modifications to the route of the road and the creation of additional separate project parts for water bodies, level changes to facilities, adjacent infrastructures, and others.
One of the elements is that there is a need to revise and reconcile the drainage plan in the contact section of 3.2 km for the two road and railway projects. line, for whose reconstruction a Building Permit and a protocol for opening a construction site have been issued.
After the revision of the drainage plan, a new corrected property boundary should be determined, which should be reflected in the PUP-PP for the road site. Also, at the intersection, the level of the railway line has been increased by 42 cm, which requires the revision of the overpass project due to a lack of height gauge. The next problem is related to the transformer station and electrical routes of the System Energy Operator, which must be relocated.
We recall that the first sod of the road was laid nearly 6 months ago, but no activities have been carried out since then.
Even during the old activities, it was clear that the project and the building permit were only for the first part of 150 meters, and for the rest they were waiting “any moment” green light.
As TrafficNews wrote, the contractor company in the person of “Trace“ refuses to sign Act 2, which starts the construction activities. The reason is that when the site is opened, the company's implementation period for the entire site begins. After the redesign, this problem should disappear and the company should start the activities.
We recall that the entire route is approximately 5 km long. With the construction of the section, the transit traffic coming from the “Trakia“ motorway and Svilengrad in the direction of road II-86 Plovdiv - Asenovgrad and Smolyan will be removed from the regional city. The investment is over 41 million leva. and the funds are from the republican budget.